# Rhino Equity, LLC: TxDOT maintenance contract 91% complete, FM0109, Austin County ($230,440, 1 sub)

**Score:** 25/100

| Field | Value |
|---|---|
| Prime contractor | Rhino Equity, LLC |
| Subcontractors | Guevara-Perez, INC (80.95%) |
| Progress | 90.56% complete, 100% of time used |
| Amount | $230,440 revised (original $211,981) |
| Change orders | $18,458 |
| Paid to date | $208,676 |
| Work | Maintenance |
| Location | FM0109, AUSTIN AND COLORADO to ., Austin County, Yoakum District |
| Let / began | 2024-05-21 / 2024-10-28 |
| Latest estimate | 2026-10-02 |
| Contract number | 5241320 |

## Why this score


Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.