# Richard Drake Construction Company, L.P.: TxDOT overlay contract 95% complete, US 82, Lamar County ($4,828,806, 6 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Richard Drake Construction Company, L.P. |
| Subcontractors | J. H. Oden Contracting Company (0.11%); East Texas R & D Services, INC. (10.03%); Highway 19 Construction LLC (2.21%); Surface Preparation Technologies, LLC (0.29%); Striping Technology, L.P. (4.31%); Texop Construction (1.26%) |
| Progress | 94.58% complete, 54.17% of time used |
| Amount | $4,828,806 revised (original $4,740,741) |
| Change orders | $-15,757 |
| Paid to date | $4,468,917 |
| Work | Overlay |
| Location | US 82, US 82 FROM 42ND ST TO DIVISION ST, Lamar County, Paris District |
| Let / began | 2024-04-05 / 2025-05-02 |
| Latest estimate | 2026-10-05 |
| Contract number | 4243214 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.