# Rk Hall, LLC: TxDOT overlay contract 17% complete, US 287, Childress County ($5,195,052, 8 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Rk Hall, LLC |
| Subcontractors | Fc Traffic Control, INC. (0.46%); Structural Integrity Group LLC (11.13%); Texas Panhandle Construction, INC. (2.35%); Wolfe Construction Group, Incorporated (0.59%); Alamo Brothers Concrete INC (5.16%); Dustin Allen, INC. (1.79%); Texop Construction (1.12%); Surface Preparation Technologies, LLC (0.3%) |
| Progress | 16.51% complete, 76.92% of time used |
| Amount | $5,195,052 revised (original $5,183,756) |
| Change orders | $11,295 |
| Paid to date | $857,789 |
| Work | Overlay |
| Location | US 287, HALL C/L, EAST to 2100' WEST OF FM 164, Childress County, Childress District |
| Let / began | 2025-11-06 / 2026-04-13 |
| Latest estimate | 2026-10-05 |
| Contract number | 11253212 |

## Why this score
- Contract over $1M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.