# Rk Hall, LLC: TxDOT overlay contract 42% complete, US 67, Irion County ($54,759,079, 10 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Rk Hall, LLC |
| Subcontractors | Dk Contracting, LLC (0.04%); Double A Contracting, L.P. (0.27%); Rpv Construction, LLC (2.38%); J. H. Oden Contracting Company (0.01%); Contractors Service, LTD. (0.21%); Relmco, INC. (9.74%); Dustrol, INC. (0.7%); Professional Traffic Control LLC (0.15%); Trp Construction Group, LLC (1.62%); W. S. Construction Company (7.96%) |
| Progress | 41.77% complete, 80.8% of time used |
| Amount | $54,759,079 revised (original $52,231,941) |
| Change orders | $389,497 |
| Paid to date | $21,981,589 |
| Work | Overlay |
| Location | US 67, TOM GREEN COUNTY LINE to 10.2 MI SOUTH OF TOM GREEN CO LINE, Irion County, San Angelo District |
| Let / began | 2024-08-02 / 2025-02-06 |
| Latest estimate | 2026-10-06 |
| Contract number | 8243203 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.