# Rk Hall, LLC: TxDOT rehabilitation of existing road contract 76% complete, SH 349, Dawson County ($18,376,448, 5 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Rk Hall, LLC |
| Subcontractors | Wims Environmental Construction, LTD. (0.48%); Murray Construction (0.83%); A Brothers Milling, LLC (0.26%); Double A Contracting, L.P. (3.7%); Industrial Fabrics, INC. (13.34%) |
| Progress | 75.79% complete, 76.35% of time used |
| Amount | $18,376,448 revised (original $17,135,619) |
| Paid to date | $12,987,646 |
| Work | Rehabilitation Of Existing Road |
| Location | SH 349, FM 2052 to MARTIN COUNTY LINE, Dawson County, Lubbock District |
| Let / began | 2025-09-05 / 2026-04-01 |
| Latest estimate | 2026-10-06 |
| Contract number | 9253238 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.