# Ronald R. Wagner & Co., LP: TxDOT seal coat contract 100%+ complete, IH 35, Webb County ($4,783,105, 2 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Ronald R. Wagner & Co., LP |
| Subcontractors | Mpb, INC. (1.3%); C.L. Wagner, LLC (2.57%) |
| Progress | 104.29% complete, 95% of time used |
| Amount | $4,783,105 revised (original $4,828,839) |
| Change orders | $-45,734 |
| Paid to date | $4,988,297 |
| Work | Seal Coat |
| Location | IH 35, 1.1 MI NORTH OF US 83 (WFR) to 0.945 MI NORTH OF CALLAGHAN INTCHG, Webb County, Laredo District |
| Let / began | 2025-09-04 / 2026-04-14 |
| Latest estimate | 2026-10-02 |
| Contract number | 9253012 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.