# Ross Sa Enterprise LLC: TxDOT maintenance contract 90% complete, US0075, Collin County ($636,712, 2 subs)

**Score:** 35/100

| Field | Value |
|---|---|
| Prime contractor | Ross Sa Enterprise LLC |
| Subcontractors | Saber Highways LLC (0%); Elite Castle Resources LLC (0%) |
| Progress | 89.94% complete, 80% of time used |
| Amount | $636,712 revised (original $281,455) |
| Change orders | $356,013 |
| Paid to date | $573,349 |
| Work | Maintenance |
| Location | US0075, VARIOUS LOCATIONS IN THE COLLIN to COUNTY MAINTENANCE SECTION, Collin County, Dallas District |
| Let / began | 2025-11-12 / 2025-12-08 |
| Latest estimate | 2026-09-29 |
| Contract number | 11251807 |

## Why this score
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.