# Roy Jorgensen Associates, INC.: TxDOT restoration contract 51% complete, US 75, Collin County ($2,700,351, 1 sub)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Roy Jorgensen Associates, INC. |
| Subcontractors | A.N.E. Concrete Cutting LLC (4.96%) |
| Progress | 50.86% complete, 59.18% of time used |
| Amount | $2,700,351 revised (original $2,620,351) |
| Paid to date | $1,332,772 |
| Work | Restoration |
| Location | US 75, GRAYSON COUNTY LINE to VALLEY CREEK TRAIL, Collin County, Dallas District |
| Let / began | 2025-10-09 / 2026-03-23 |
| Latest estimate | 2026-10-05 |
| Contract number | 10253220 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.