# Roy Jorgensen Associates, INC.: TxDOT maintenance contract 86% complete, IH0010, Bexar County ($39,681,479, 4 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Roy Jorgensen Associates, INC. |
| Subcontractors | Boen Landscaping & Irrigation, LLC (0%); Yes America Now, INC. (0%); Bk Field Operations LLC (0%); Alamo1 (0%) |
| Progress | 86.2% complete, 87.6% of time used |
| Amount | $39,681,479 revised (original $17,507,039) |
| Change orders | $22,174,440 |
| Paid to date | $34,206,653 |
| Work | Maintenance |
| Location | IH0010, VARIOUS LOCATIONS IN to BEXAR COUNTY, Bexar County, San Antonio District |
| Let / began | 2023-01-06 / 2023-04-01 |
| Latest estimate | 2026-10-02 |
| Contract number | 1234207 |

## Why this score
- Contract over $10M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.