# Roy Jorgensen Associates, INC.: TxDOT maintenance contract 65% complete, IH0035E, Dallas County ($16,740,386, 1 sub)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Roy Jorgensen Associates, INC. |
| Subcontractors | Stripe-A-Zone, LLC (0%) |
| Progress | 64.71% complete, 89.36% of time used |
| Amount | $16,740,386 revised (original $3,650,662) |
| Change orders | $13,097,482 |
| Paid to date | $10,837,002 |
| Work | Maintenance |
| Location | IH0035E, VARIOUS ROADWAYS IN to DALLAS AND TARRANT COUNTY, Dallas County, Dallas District |
| Let / began | 2021-02-05 / 2021-05-18 |
| Latest estimate | 2026-10-05 |
| Contract number | 2214207 |

## Why this score
- Contract over $10M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.