# Roy Jorgensen Associates, INC.: TxDOT maintenance contract 64% complete, IH0045, Walker County ($28,823,993, 4 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Roy Jorgensen Associates, INC. |
| Subcontractors | Cedar Hill Services, LLC (0%); The Street Cleaner LLC (0%); Cornerstone Paving And Construction, L.L.C. (0%); Jackson Excavation, LLC (0%) |
| Progress | 63.68% complete, 70.91% of time used |
| Amount | $28,823,993 revised (original $13,514,343) |
| Change orders | $15,310,927 |
| Paid to date | $18,356,531 |
| Work | Maintenance |
| Location | IH0045, MONTGOMERY/WALKER COUNTY LINE to FREESTONE/NAVARRO COUNTY LINE, Walker County, Bryan District |
| Let / began | 2022-03-03 / 2022-07-01 |
| Latest estimate | 2026-10-02 |
| Contract number | 3224006 |

## Why this score
- Contract over $10M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.