# Rpm Xconstruction, LLC: TxDOT widen freeway contract 54% complete, US 75, Grayson County ($97,532,603, 19 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Rpm Xconstruction, LLC |
| Subcontractors | Dallas Lite And Barricade, INC. (0.02%); Texas Select Erosion, LLC (0.72%); Overland Corporation (0.72%); Texop Construction (0.31%); Rpm Utilities, LLC (5.17%); Paniolo Construction Services, LLC (5.87%); J. E. Guzman Construction, INC. (0.26%); Straight Line Sawing & Sealing, INC. (0.21%); Albatross Construction LLC (4.66%); Southern Cross Contractors, LLC (1.11%); Dfw Rebar, INC. (0.55%); Wims Environmental Construction, LTD. (3.82%); Skaggs Road Boring, INC. (0.35%); Wylie Drilling & Drainage, INC. (0.31%); Cyclone Services LLC (0.09%); A R Daniel Construction Services, Incorporated (0.44%); Legacy Underground LLC (0%); Trp Construction Group, LLC (1.26%); Blue Rock Drilling, LLC (0%) |
| Progress | 53.66% complete, 39.61% of time used |
| Amount | $97,532,603 revised (original $96,348,356) |
| Change orders | $414,226 |
| Paid to date | $51,920,860 |
| Work | Widen Freeway |
| Location | US 75, US 75 FRO COLLIN COUNTY LINE TO FM 902, Grayson County, Paris District |
| Let / began | 2024-11-07 / 2025-05-05 |
| Latest estimate | 2026-10-06 |
| Contract number | 11243202 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.