# Sak Construction, LLC: TxDOT miscellaneous construction contract 38% complete, IH 35, Travis County ($715,932,876, 34 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Sak Construction, LLC |
| Subcontractors | National Welding Corporation (0.03%); Ram Concrete & General Construction (0.67%); J.A. Road Boring, INC. (0%); Certified Arbor Care, INC. (0.02%); Certerra Instrumentation And Monitoring, LLC (1.39%); Zara Environmental, LLC (0%); National Power Rodding Corporation (0%); (Inactive)stripe It Up, LLC (0%); Keller North America, INC. (1.82%); Transystems Corporation Consultants (0%); Fibertel, LLC (0%); Wgi, INC. (0%); A K Fuquay Construction (0.02%); Badger Daylighting Corp. (0%); Rami Transportation, INC. (1.84%); Mccall Drilling Hdd INC (0.01%); Beaird Drilling Services, INC. (0.01%); Fuquay, INC. (0%); Matt Chlor Texas, LLC (0%); Turnkey Pump Services LLC (0%); Superior Traffic Control, LLC (0.02%); Ella S.A. Contracting, L.P. (1.15%); Behrens And Associates, INC. (0.95%); Terracon Consultants, INC. (0%); Bleu Bison Wash Solutions (0%); Texas Site Services, LLC (0.01%); Northern Lights Group LLC (0%); The Levy Company, LLC (0.1%); Frank Jr Reinforcement LLC (0.59%); Doran Steel, INC. (0.46%); Lone Star Paving Company (0%); Redcap Staffing (0.01%); Accurate Drilling & Construction, Incorporated (0%); Texas Cutting & Coring Gp, INC. (0.01%) |
| Progress | 37.77% complete, 33.22% of time used |
| Amount | $715,932,876 revised (original $698,120,715) |
| Change orders | $415,348 |
| Paid to date | $263,866,917 |
| Work | Miscellaneous Construction |
| Location | IH 35, SOUTH OF 51ST STREET to NORTH OF HOLLY STREET, Travis County, Austin District |
| Let / began | 2024-12-04 / 2025-05-14 |
| Latest estimate | 2026-10-05 |
| Contract number | 12243201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.