# Salinas Construction Technologies, LTD.: TxDOT bridge replacement contract 100%+ complete, FM 2200, Medina County ($6,508,357, 7 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Salinas Construction Technologies, LTD. |
| Subcontractors | D&G Energy Corporation (0.75%); Robin Steel LLC (0.16%); Toro Bravo Construction, LLC (0.15%); Southeast Grinding And Grooving LLC (0.11%); Texas Shafts, INC. (1.57%); Flasher Equipment Company (2.12%); King George Traffic Solutions LLC (0.31%) |
| Progress | 103.42% complete, 99.04% of time used |
| Amount | $6,508,357 revised (original $6,206,529) |
| Change orders | $301,828 |
| Paid to date | $6,730,999 |
| Work | Bridge Replacement |
| Location | FM 2200, AT SAN FRANCISCO CREEK to ., Medina County, San Antonio District |
| Let / began | 2023-03-08 / 2023-05-01 |
| Latest estimate | 2026-10-05 |
| Contract number | 3233218 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.