# Salinas Construction Technologies, LTD.: TxDOT rehabilitation of existing road contract 73% complete, FM 462, Medina County ($7,028,828, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Salinas Construction Technologies, LTD. |
| Subcontractors | Avila And Son's L.L.C. (2.36%); Buyers Barricades San Antonio, LLC (0.41%); Centerline Technologies, LLC (6.74%); Ross Sa Enterprise LLC (1.27%) |
| Progress | 73.3% complete, 90.59% of time used |
| Amount | $7,028,828 revised (original $6,964,197) |
| Change orders | $64,631 |
| Paid to date | $5,152,341 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 462, BENTLEY CROSSING to CR 433, Medina County, San Antonio District |
| Let / began | 2024-06-06 / 2024-10-15 |
| Latest estimate | 2026-10-05 |
| Contract number | 6243215 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.