# Scout 5 Construction LLC: TxDOT bridge replacement contract 38% complete, FM 1300, Wharton County ($2,698,780, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Scout 5 Construction LLC |
| Subcontractors | M & D Foundation Drilling Industries, INC. (10.38%); Traffic Signs & Lines, LLC (1.77%); Matagorda Construction & Materials (3.2%); Toro Bravo Construction, LLC (0%) |
| Progress | 38.1% complete, 41.4% of time used |
| Amount | $2,698,780 revised (original $2,667,278) |
| Paid to date | $1,016,251 |
| Work | Bridge Replacement |
| Location | FM 1300, AT GOLDENROD CREEK to STR # 0420-10-010, Wharton County, Yoakum District |
| Let / began | 2025-12-02 / 2026-05-19 |
| Latest estimate | 2026-10-05 |
| Contract number | 12253024 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.