# Scout 5 Construction LLC: TxDOT bridge replacement contract 43% complete, CS, Matagorda County ($3,211,346, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Scout 5 Construction LLC |
| Subcontractors | Mesa Rod Busters INC (0.23%); Matagorda Construction & Materials (0.77%); M & D Foundation Drilling Industries, INC. (11.77%); Vizion Crane & Industrial Support, LLC (1.73%) |
| Progress | 42.88% complete, 51.31% of time used |
| Amount | $3,211,346 revised (original $3,170,844) |
| Paid to date | $1,359,703 |
| Work | Bridge Replacement |
| Location | CS, AT COTTONWOOD CREEK to STR# B005-20-002, Matagorda County, Yoakum District |
| Let / began | 2025-02-06 / 2025-10-30 |
| Latest estimate | 2026-10-05 |
| Contract number | 2253033 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.