# Select Maintenance, L.L.C.: TxDOT hazard elimination & safety contract 71% complete, Various, Harris County ($6,371,757, 2 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Select Maintenance, L.L.C. |
| Subcontractors | Traffic Signs & Lines, LLC (46.65%); Bay City Traffic (14.48%) |
| Progress | 71.18% complete, 90.91% of time used |
| Amount | $6,371,757 revised (original $5,909,098) |
| Change orders | $344,645 |
| Paid to date | $4,451,254 |
| Work | Hazard Elimination & Safety |
| Location | Various, VARIOUS LOCATIONS ON IH 610 & SL 8 to ., Harris County, Houston District |
| Let / began | 2022-08-03 / 2023-04-26 |
| Latest estimate | 2026-09-30 |
| Contract number | 8223011 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.