# Sema Construction, INC.: TxDOT interchange (new or reconstructed) contract 100% complete, IH 20, Parker County ($58,621,066, 28 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Sema Construction, INC. |
| Subcontractors | Luis Moreno Trucking (1.72%); Laughley Bridge & Construction, INC. (2%); Hermanos Steel, LLC (0.82%); (Inactive)royal Rebar (3.55%); Primate Construction, LP (0.03%); Dallas Lite And Barricade, INC. (0.18%); Texas Shafts, INC. (0.86%); Road Solutions L.L.C. (7.99%); Linear Traffic Markings LLC (0.47%); Roadway Specialties, INC. (0.03%); USA Swppp Inspections, INC. (0.43%); Act Saw Cutting & Removal (0.13%); Wims Environmental Construction, LTD. (0.99%); Synergy Signs & Services LLC (1.39%); A Brothers Milling, LLC (0.17%); Paniolo Construction Services, LLC (0.25%); Rambo Contracting, INC. (3.36%); Lindamood, INC. (0.2%); Alliance Geotechnical Group, INC. (0.02%); J.H. Painting Company (0.11%); Hdz Construction (0.03%); Allied Drilling Company (0.06%); Reynolds Asphalt & Construction Company (5.46%); Professional Traffic Control LLC (0.04%); Fortson Contracting, INC. (0.22%); Buyers Barricades, INC. (0.01%); Econolite Systems, INC. (1.14%); Southeast Grinding And Grooving LLC (0.04%) |
| Progress | 99.65% complete, 95.32% of time used |
| Amount | $58,621,066 revised (original $54,398,492) |
| Change orders | $3,724,165 |
| Paid to date | $57,920,897 |
| Work | Interchange (New Or Reconstructed) |
| Location | IH 20, IH 20/IH 30 SPLIT to TARRANT/PARKER COUNTY LINE, Parker County, Fort Worth District |
| Let / began | 2023-05-04 / 2023-08-28 |
| Latest estimate | 2026-09-30 |
| Contract number | 5233002 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.