# Sema Construction, INC.: TxDOT widen freeway contract 97% complete, SH 199, Tarrant County ($124,393,166, 30 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Sema Construction, INC. |
| Subcontractors | Panther Creek Transportation, INC. (0.23%); A R Daniel Construction Services, Incorporated (0.45%); Comen Enterprise LLC (0.04%); Mcl Contracting, LLC (0.2%); Striping Technology, L.P. (0.25%); Texas Environmental Management - San Antonio, INC. (0.45%); Ats Drilling, INC. (7.09%); (Inactive)royal Rebar (4.53%); Laughley Bridge & Construction, INC. (0.72%); A Brothers Milling, LLC (0.16%); Wg Engineering & Construction, LLC (0.75%); Buyers Barricades, INC. (0.01%); Reynolds Asphalt & Construction Company (4.5%); Dustrol, INC. (0.02%); Primate Construction, LP (0.21%); J.H. Painting Company (0.05%); W.O.E. Construction, INC. (0.75%); Paniolo Construction Services, LLC (1.29%); (Inactive)brenda Price Trucking (0.25%); Mica Corporation (1.15%); Breda Company, INC. (0%); Dywidag-Systems International_usa,INC. (0.08%); USA Amtech, INC. (0.06%); Fortson Contracting, INC. (0.07%); Antigo Construction, INC. (0.08%); Medellin Hdd LLC (0%); Fga Construction LLC (0.03%); Sweeping Corporation Of America, LLC (0.06%); Trp Construction Group, LLC (0.18%); Southeast Grinding And Grooving LLC (0.06%) |
| Progress | 96.58% complete, 78.46% of time used |
| Amount | $124,393,166 revised (original $103,766,994) |
| Change orders | $19,558,719 |
| Paid to date | $119,105,383 |
| Work | Widen Freeway |
| Location | SH 199, NORTH OF FM 1886 to S END OF LAKE WORTH BR, Tarrant County, Fort Worth District |
| Let / began | 2020-06-04 / 2020-09-28 |
| Latest estimate | 2026-10-05 |
| Contract number | 6203002 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.