# Sema Construction, INC.: TxDOT rehabilitation of existing road contract 98% complete, FM 730, Wise County ($39,021,652, 20 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Sema Construction, INC. |
| Subcontractors | Lindamood, INC. (0.16%); Farr Foundation, INC. (0.44%); Texas Environmental Management - San Antonio, INC. (0.76%); Southeast Grinding And Grooving LLC (0.04%); Toro Bravo Construction, LLC (0.33%); Elite Striping, LLC (0.08%); Mar-Zap Construction, LLC (0.44%); Alliance Geotechnical Group, INC. (0.28%); A Brothers Milling, LLC (0.36%); Lollar Construction Group LLC (2.83%); Rambo Contracting, INC. (2.7%); Reinhold Electric, INC (1.69%); Synergy Signs & Services LLC (0.2%); USA Swppp Inspections, INC. (0.65%); Wylie Drilling & Drainage, INC. (2.29%); Dallas Lite And Barricade, INC. (0.53%); Reynolds Asphalt & Construction Company (15.47%); Dfw Rebar, INC. (0.1%); Act Saw Cutting & Removal (0.06%); West Texas Rock Resources, LLC (0.01%) |
| Progress | 97.66% complete, 99.69% of time used |
| Amount | $39,021,652 revised (original $38,322,905) |
| Change orders | $261,673 |
| Paid to date | $37,680,256 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 730, 3.479 MI N OF SH 114 to SH 114 IN BOYD, Wise County, Fort Worth District |
| Let / began | 2023-08-03 / 2024-02-19 |
| Latest estimate | 2026-10-05 |
| Contract number | 8233205 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.