# Ser Construction Partners, LLC: TxDOT widen freeway contract 62% complete, FM 1518, Bexar County ($74,339,229, 17 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Ser Construction Partners, LLC |
| Subcontractors | Fibertel, LLC (0%); Texas Materials Group, INC. (18.9%); C & C Alcoser Trucking (0.08%); G & D Direccional (0.24%); Prv Services, INC. (0.42%); Dnr Roadway Contractors, LLC (2.63%); Montalvo Bridge Systems, LLC (0.07%); Aaron Concrete Contractors, LLC (0.57%); Beaird Drilling Services, INC. (0.56%); Dakota Utility Contractors, INC. (0.33%); Tex Op Construction, LP (1.18%); E-Z Bel Construction, LLC (1.79%); Texas Environmental Management - San Antonio, INC. (2.64%); K&A Rebar & Post-Tension LLC (0.03%); Rangeline Tapping Services, INC. (0.01%); Badeco, INC. (2.61%); Trp Construction Group, LLC (0.98%) |
| Progress | 62.16% complete, 58.32% of time used |
| Amount | $74,339,229 revised (original $72,780,035) |
| Change orders | $1,559,195 |
| Paid to date | $46,210,358 |
| Work | Widen Freeway |
| Location | FM 1518, FM 78 to IH 10 E, Bexar County, San Antonio District |
| Let / began | 2023-10-05 / 2024-04-10 |
| Latest estimate | 2026-10-06 |
| Contract number | 10233002 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.