# Ser Construction Partners, LLC: TxDOT overlay contract 79% complete, SH 99, Harris County ($6,696,149, 9 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Ser Construction Partners, LLC |
| Subcontractors | Prv Services, INC. (0.38%); Shaw Drilling, LLC (0.04%); Deco Contractors, INC. (2.37%); Stripe Lines, INC. (0.92%); C & C Traffic Control (0.18%); Montalvo Bridge Systems, LLC (0.53%); Semarck Landscape Services, INC. (4.1%); Rs&Ds Services, LLC (0.18%); Curb Planet INC. (0.16%) |
| Progress | 78.52% complete, 58.26% of time used |
| Amount | $6,696,149 revised (original $6,547,219) |
| Change orders | $8,928 |
| Paid to date | $5,148,188 |
| Work | Overlay |
| Location | SH 99, LONGENBAUGH to FM 529, Harris County, Houston District |
| Let / began | 2025-10-08 / 2026-03-16 |
| Latest estimate | 2026-09-30 |
| Contract number | 10253011 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.