# Ser Construction Partners, LLC: TxDOT interchange (new or reconstructed) contract 50% complete, US 90, Liberty County ($29,982,356, 13 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Ser Construction Partners, LLC |
| Subcontractors | Montalvo Bridge Systems, LLC (0.5%); Mesa Rod Busters INC (0.17%); M & D Foundation Drilling Industries, INC. (4.5%); Creacom, INC. (1.85%); C & C Traffic Control (0.04%); Seamarck Landscape Services, INC (0.09%); Tex Op Construction, LP (0.58%); Cherry Moving Company, INC. (0.39%); Semarck Landscape Services, INC. (0.09%); Stripe Lines, INC. (0.38%); Keller North America, INC. (0.32%); Rs&Ds Services, LLC (0.17%); Curb Planet INC. (0.01%) |
| Progress | 49.98% complete, 44.61% of time used |
| Amount | $29,982,356 revised (original $27,266,206) |
| Change orders | $2,716,151 |
| Paid to date | $14,985,337 |
| Work | Interchange (New Or Reconstructed) |
| Location | US 90, AT UP RAILROAD to ., Liberty County, Beaumont District |
| Let / began | 2024-11-06 / 2025-07-18 |
| Latest estimate | 2026-10-01 |
| Contract number | 11243005 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.