# Ser Construction Partners, LLC: TxDOT miscellaneous construction contract 99% complete, FM 518, Galveston County ($16,221,975, 13 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Ser Construction Partners, LLC |
| Subcontractors | Willow City Sign & Rail, INC. (0.28%); Semarck Landscape Services, INC. (0.59%); D. Solis Trucking, INC. (0.64%); Third Coast Services LLC (0.82%); Scott Derr Painting Co, LLC (0.03%); Specialty Drilling, LLC (1.03%); Montalvo Bridge Systems, LLC (0.12%); A. Sanchez Trucking (0.49%); C & C Traffic Control (0.14%); Prv Services, INC. (0.15%); Specialized Maintenance Services, INC. (0.04%); Coastal Foundation Drilling Co., INC. (1.04%); Stripe Lines, INC. (2.29%) |
| Progress | 99.29% complete, 98.73% of time used |
| Amount | $16,221,975 revised (original $15,447,120) |
| Change orders | $724,846 |
| Paid to date | $16,056,624 |
| Work | Miscellaneous Construction |
| Location | FM 518, JAMES ROSS ELEMENTARY SCHOOL to PALOMINO ROAD, Galveston County, Houston District |
| Let / began | 2024-01-04 / 2024-03-08 |
| Latest estimate | 2026-09-30 |
| Contract number | 1243005 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.