# Skyline Bridge LLC: TxDOT bridge replacement contract 83% complete, SH 79, Archer County ($3,352,238, 7 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Skyline Bridge LLC |
| Subcontractors | West Texas Rock Resources, LLC (0.22%); Wolfe Construction Group, Incorporated (0.64%); Peachtree Construction, LTD. (15.03%); Morris County Contractors, L.L.C. (3.37%); Striping Technology, L.P. (1.85%); Fc Traffic Control, INC. (0.23%); Dustrol, INC. (0.28%) |
| Progress | 82.92% complete, 179.55% of time used |
| Amount | $3,352,238 revised (original $3,345,238) |
| Paid to date | $2,773,858 |
| Work | Bridge Replacement |
| Location | SH 79, SH 79 AT BLUFF CREEK to ., Archer County, Wichita Falls District |
| Let / began | 2025-01-07 / 2025-04-15 |
| Latest estimate | 2026-10-01 |
| Contract number | 1253026 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.