# Skyline Bridge LLC: TxDOT bridge replacement contract 98% complete, CS, Denton County ($1,695,057, 7 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Skyline Bridge LLC |
| Subcontractors | Marcoms Construction LLC (0.53%); Peachtree Construction, LTD. (3.01%); Hudson, INC. South (1.07%); Morris County Contractors, L.L.C. (1.27%); Diamond Elite Barricades, LLC (0.42%); Southwest Construction Services (0.19%); USA Swppp Inspections, INC. (0.68%) |
| Progress | 98.35% complete, 190.29% of time used |
| Amount | $1,695,057 revised (original $1,636,169) |
| Change orders | $26,188 |
| Paid to date | $1,634,914 |
| Work | Bridge Replacement |
| Location | CS, TRINITY ROAD AT COOPER CREEK to IN CITY OF DENTON, Denton County, Dallas District |
| Let / began | 2025-09-04 / 2025-11-19 |
| Latest estimate | 2026-10-02 |
| Contract number | 9253024 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.