# Southern Road & Bridge, LLC: TxDOT bridge widening or rehabilitation contract 99% complete, SH 73, Jefferson County ($11,757,366, 8 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Southern Road & Bridge, LLC |
| Subcontractors | Trp Construction Group, LLC (4%); Select Maintenance, L.L.C. (0%); American Remediation Options, INC. (0.34%); Texas Materials Group, INC. (4.63%); King George Traffic Solutions LLC (0%); Wims Environmental Construction, LTD. (1.43%); Ragle Construction, INC. (14.89%); Skidabrader Group LLC (2.98%) |
| Progress | 98.69% complete, 91.37% of time used |
| Amount | $11,757,366 revised (original $10,927,788) |
| Change orders | $829,578 |
| Paid to date | $11,603,197 |
| Work | Bridge Widening Or Rehabilitation |
| Location | SH 73, AT RAINBOW BRIDGE to ., Jefferson County, Beaumont District |
| Let / began | 2024-02-01 / 2024-06-12 |
| Latest estimate | 2026-10-01 |
| Contract number | 2243009 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.