# Sterling Delaware Holding Company: TxDOT widen non-freeway contract 98% complete, SH 99, Fort Bend County ($12,533,526, 21 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Sterling Delaware Holding Company |
| Subcontractors | Delena Construction Services LLC (1.14%); A Brothers Milling, LLC (0.08%); (Inactive)mesa Rod Busters, INC. (0.33%); Superior Grouting Services, INC. (0.11%); Penhall Company (0.03%); Scott Derr Painting Co, LLC (0.12%); Highway 1 LLC (0.6%); Curb Planet INC. (0.04%); Cpave, INC. (0.09%); Willow City Sign & Rail, INC. (1.45%); Rdi Foundation Drilling (1.81%); Bortunco (0.9%); Texas Environmental Management - San Antonio, INC. (1.17%); Chlor-Serv, INC. (0.05%); Eubank Excavation, L.L.C. (0.29%); Koppl Pipeline Services, INC (0.61%); Flovera Construction Services, LLC (6.62%); Third Coast Services LLC (1.44%); Gmj Paving Co. (1.91%); Lonestar Traffic Safety, LLC (0.08%); Jb Pinnacle Group, LLC (0.38%) |
| Progress | 98.19% complete, 108.77% of time used |
| Amount | $12,533,526 revised (original $12,117,582) |
| Change orders | $331,890 |
| Paid to date | $12,223,561 |
| Work | Widen Non-Freeway |
| Location | SH 99, WESTHEIMER PKWY to CINCO RANCH BLVD, Fort Bend County, Houston District |
| Let / began | 2023-04-04 / 2023-07-17 |
| Latest estimate | 2026-09-30 |
| Contract number | 4233009 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.