# Structural Integrity Group LLC: TxDOT bridge widening or rehabilitation contract 60% complete, Various, Dewitt County ($1,956,224, 7 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Structural Integrity Group LLC |
| Subcontractors | Cherokee Services (5.61%); South Texas Traffic Alliance INC. (1.2%); Highway Barricades And Services, LLC (7.61%); Tex Op Construction, LP (0.71%); Superior Traffic Control, LLC (1.01%); Jones Fish And Hatcheries & Distributors LLC (2.4%); Clear Restoration, LLC (0.28%) |
| Progress | 60.47% complete, 64.47% of time used |
| Amount | $1,956,224 revised (original $1,923,922) |
| Paid to date | $1,163,443 |
| Work | Bridge Widening Or Rehabilitation |
| Location | Various, DISTRICTWIDE to ., Dewitt County, Yoakum District |
| Let / began | 2025-12-02 / 2026-04-22 |
| Latest estimate | 2026-10-05 |
| Contract number | 12253020 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.