# Structural Integrity Group LLC: TxDOT bridge widening or rehabilitation contract 100%+ complete, Various, Travis County ($1,176,361, 2 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Structural Integrity Group LLC |
| Subcontractors | Cherokee Services (0.59%); South Texas Traffic Alliance INC. (0.1%) |
| Progress | 227.62% complete, 63.02% of time used |
| Amount | $1,176,361 revised (original $865,709) |
| Change orders | $287,450 |
| Paid to date | $2,624,765 |
| Work | Bridge Widening Or Rehabilitation |
| Location | Various, VARIOUS LOCATIONS IN BURNET, LLANO, to MASON AND GILLESPIE COUNTIES., Travis County, Austin District |
| Let / began | 2025-05-02 / 2025-09-02 |
| Latest estimate | 2026-10-05 |
| Contract number | 5253222 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.