# Sundt Construction, INC.: TxDOT widen freeway contract 72% complete, IH 20, Ector County ($241,789,127, 25 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Sundt Construction, INC. |
| Subcontractors | Hjc Farms, INC. (1.29%); Surface Preparation Technologies, LLC (0.03%); Fc Traffic Control, INC. (0.6%); A Brothers Milling, LLC (0.27%); Scott Derr Painting Co, LLC (0.08%); Primate Construction, LP (0.06%); Speedy Paving (0.3%); J. H. Oden Contracting Company (0.21%); Breda Company, INC. (0%); J Force Transportation LLC (0.23%); Peyson Transport, LLC (0%); Kelly Evans Construction, LLC (0.05%); Thorcon Shotcrete And Shoring LLC (0.21%); Toro Bravo Construction, LLC (5.01%); Dk Contracting, LLC (0.19%); Hawk Construction (0.07%); Fibertex, LLC (0.03%); West Texas Rock Resources, LLC (0.74%); Dtm Trucking, INC. (3.18%); Trp Construction Group, LLC (0.66%); Willis Electric Co., LP (4.89%); Mica Corporation (0.72%); Lone Star Paving Company (11.02%); Fusion Communications, LLC (0.03%); Hernandez Oilfield Transportation LLC (0.31%) |
| Progress | 72.48% complete, 71.46% of time used |
| Amount | $241,789,127 revised (original $237,861,190) |
| Change orders | $1,258,628 |
| Paid to date | $173,321,540 |
| Work | Widen Freeway |
| Location | IH 20, EAST OF JBS PARKWAY to MIDLAND COUNTY LINE, Ector County, Odessa District |
| Let / began | 2023-11-02 / 2024-05-16 |
| Latest estimate | 2026-10-01 |
| Contract number | 11233201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.