# Sundt Construction, INC.: TxDOT widen freeway contract 74% complete, IH 20, Midland County ($165,350,370, 22 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Sundt Construction, INC. |
| Subcontractors | Willis Electric Co., LP (6.67%); Texop Construction (0.5%); Hjc Farms, INC. (0.82%); Primate Construction, LP (0.06%); Dtm Trucking, INC. (2.71%); Surface Preparation Technologies, LLC (0.04%); Dk Contracting, LLC (0.19%); Toro Bravo Construction, LLC (0.85%); Trp Construction Group, LLC (0.87%); Fc Traffic Control, INC. (0.94%); West Texas Rock Resources, LLC (0.42%); J Force Transportation LLC (0.34%); Peyson Transport, LLC (0%); Kelly Evans Construction, LLC (0.07%); J. H. Oden Contracting Company (0.35%); Hawk Construction (0.11%); Scott Derr Painting Co, LLC (0.11%); Speedy Paving (0.27%); Lone Star Paving Company (10.5%); Fusion Communications, LLC (0.01%); Mica Corporation (0.52%); Hernandez Oilfield Transportation LLC (1.01%) |
| Progress | 73.99% complete, 70.93% of time used |
| Amount | $165,350,370 revised (original $162,898,983) |
| Change orders | $222,625 |
| Paid to date | $120,701,806 |
| Work | Widen Freeway |
| Location | IH 20, EAST OF CR 1300 TO EAST OF CR 1250, Midland County, Odessa District |
| Let / began | 2024-03-06 / 2024-07-29 |
| Latest estimate | 2026-09-30 |
| Contract number | 3243201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.