# Synergy Project Contractors, INC.: TxDOT maintenance contract 87% complete, IH0010, El Paso County ($1,338,383)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Synergy Project Contractors, INC. |
| Progress | 86.77% complete, 99.29% of time used |
| Amount | $1,338,383 revised (original $1,271,955) |
| Change orders | $66,426 |
| Paid to date | $1,161,370 |
| Work | Maintenance |
| Location | IH0010, VARIOUS LOCATIONS, El Paso County, El Paso District |
| Let / began | 2025-05-01 / 2025-08-05 |
| Latest estimate | 2026-10-05 |
| Contract number | 5254006 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.