# Synergy Signs & Services LLC: TxDOT maintenance contract 81% complete, US0075, Collin County ($101,685)

**Score:** 25/100

| Field | Value |
|---|---|
| Prime contractor | Synergy Signs & Services LLC |
| Progress | 80.98% complete, 88.63% of time used |
| Amount | $101,685 revised (original $102,300) |
| Paid to date | $82,839 |
| Work | Maintenance |
| Location | US0075, DALLAS COUNTY LINE to GRAYSON COUNTY LINE, Collin County, Dallas District |
| Let / began | 2024-10-31 / 2024-12-18 |
| Latest estimate | 2026-09-29 |
| Contract number | 10241808 |

## Why this score


Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.