# Taylor Bridge LLC: TxDOT maintenance contract 78% complete, SH0081, Hill County ($1,378,562, 3 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Taylor Bridge LLC |
| Subcontractors | Dcc Construction And Services, L.L.C. (2.18%); Albeco Contractors LLC (36.32%); S&S Bridge Painting (12.86%) |
| Progress | 78.29% complete, 93.27% of time used |
| Amount | $1,378,562 revised (original $1,179,951) |
| Change orders | $196,611 |
| Paid to date | $1,077,673 |
| Work | Maintenance |
| Location | SH0081, VARIOUS LOCATIONS to ACROSS THE WACO DISTRICT, Hill County, Waco District |
| Let / began | 2025-11-05 |
| Latest estimate | 2026-10-06 |
| Contract number | 11254002 |

## Why this score
- Contract over $1M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.