# Taylor Bridge LLC: TxDOT maintenance contract 90% complete, SH0358, Nueces County ($786,500)

**Score:** 35/100

| Field | Value |
|---|---|
| Prime contractor | Taylor Bridge LLC |
| Progress | 90.27% complete, 93.33% of time used |
| Amount | $786,500 revised (original $276,452) |
| Change orders | $509,948 |
| Paid to date | $709,845 |
| Work | Maintenance |
| Location | SH0358, VARIOUS to ., Nueces County, Corpus Christi District |
| Let / began | 2025-09-16 |
| Latest estimate | 2026-10-03 |
| Contract number | 9251601 |

## Why this score
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.