# Texas Cordia Construction, LLC: TxDOT bridge replacement contract 94% complete, CR, Hidalgo County ($2,600,173, 7 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Texas Cordia Construction, LLC |
| Subcontractors | Soil Tech Advance INC. (2.26%); Munoz Foundation Drilling, INC. (7.1%); Guerra Construction Company (0.8%); Certified Placers LLC (0.62%); Highway Barricades And Services, LLC (0.44%); Mid Valley Pest Control LLC (0.91%); Valley Striping Corp. (0.04%) |
| Progress | 94.03% complete, 78.76% of time used |
| Amount | $2,600,173 revised (original $2,537,955) |
| Paid to date | $2,386,380 |
| Work | Bridge Replacement |
| Location | CR, MILE 1 WEST RD., NBI #: 211090AA082 to @ MAIN SUPPLY CHANNEL, Hidalgo County, Pharr District |
| Let / began | 2025-01-08 / 2025-03-31 |
| Latest estimate | 2026-10-02 |
| Contract number | 1253222 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.