# Texas Cordia Construction, LLC: TxDOT rehabilitation of existing road contract 100%+ complete, FM 676, Hidalgo County ($16,639,402, 9 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Texas Cordia Construction, LLC |
| Subcontractors | G & E Escobedo Construction, INC. (0%); Rio Grande Rebar Rodbusters, LLC (0.08%); Highway Barricades And Services, LLC (1%); Gulf Coast Contractors, INC. (1.53%); Munoz Foundation Drilling, INC. (0%); Dustrol, INC. (0.8%); *austin Traffic Signal Construction Co., INC. (6.49%); Salazar Utility Construction INC. (0.38%); A-Core Concrete Cutting Of Texas, INC. (0.1%) |
| Progress | 103.28% complete, 111.5% of time used |
| Amount | $16,639,402 revised (original $15,880,158) |
| Change orders | $513,243 |
| Paid to date | $16,931,785 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 676, SH 364, EAST to SH 107, Hidalgo County, Pharr District |
| Let / began | 2023-02-01 / 2023-06-19 |
| Latest estimate | 2026-10-01 |
| Contract number | 2233011 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.