# Texas Cordia Construction, LLC: TxDOT widen non-freeway contract 95% complete, FM 676, Hidalgo County ($12,303,502, 7 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Texas Cordia Construction, LLC |
| Subcontractors | Highway Barricades And Services, LLC (1.09%); Soil Tech Advance INC. (0.6%); D&G Energy Corporation (6.4%); Rio Grande Rebar Rodbusters, LLC (0.15%); Dustrol, INC. (0.32%); Guerra Construction Company (0.21%); Certified Placers LLC (0.11%) |
| Progress | 94.68% complete, 92.09% of time used |
| Amount | $12,303,502 revised (original $11,811,612) |
| Change orders | $325,891 |
| Paid to date | $11,492,384 |
| Work | Widen Non-Freeway |
| Location | FM 676, TAYLOR RD. to FM 2220, Hidalgo County, Pharr District |
| Let / began | 2024-03-06 / 2024-07-11 |
| Latest estimate | 2026-10-01 |
| Contract number | 3243205 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.