# Texas Cordia Construction, LLC: TxDOT widen non-freeway contract 35% complete, FM 1423, Hidalgo County ($3,802,011, 3 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Texas Cordia Construction, LLC |
| Subcontractors | Texas Environmental Management - San Antonio, INC. (1.87%); Highway Barricades And Services, LLC (1.29%); Dustrol, INC. (1.35%) |
| Progress | 34.95% complete, 52.26% of time used |
| Amount | $3,802,011 revised (original $3,406,133) |
| Change orders | $341,878 |
| Paid to date | $1,309,942 |
| Work | Widen Non-Freeway |
| Location | FM 1423, BUS 83S to CR 3677 /END OF STATE MAINTENANCE, Hidalgo County, Pharr District |
| Let / began | 2025-07-01 / 2025-11-21 |
| Latest estimate | 2026-10-05 |
| Contract number | 7253014 |

## Why this score
- Contract over $1M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.