# Texas Cordia Construction, LLC: TxDOT widen non-freeway contract 29% complete, SH 107, Hidalgo County ($32,410,804, 6 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Texas Cordia Construction, LLC |
| Subcontractors | Texas Highway Systems, INC. (0.28%); Highway Barricades And Services, LLC (1.38%); Electro-Hi, LLC (0.18%); *austin Traffic Signal Construction Co., INC. (2.02%); Dustrol, INC. (0.76%); Munoz Foundation Drilling, INC. (0%) |
| Progress | 28.85% complete, 14.83% of time used |
| Amount | $32,410,804 revised (original $32,261,532) |
| Paid to date | $9,306,826 |
| Work | Widen Non-Freeway |
| Location | SH 107, SH 495 to FM 1924, Hidalgo County, Pharr District |
| Let / began | 2025-09-04 / 2026-04-13 |
| Latest estimate | 2026-10-02 |
| Contract number | 9253002 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.