# Texas Drainage INC.: TxDOT maintenance contract 89% complete, US0287, Trinity County ($333,701)

**Score:** 25/100

| Field | Value |
|---|---|
| Prime contractor | Texas Drainage INC. |
| Progress | 89.34% complete, 78.67% of time used |
| Amount | $333,701 revised (original $333,950) |
| Paid to date | $298,340 |
| Work | Maintenance |
| Location | US0287, VARIOUS LOCATIONS IN TRINITY COUNTY to MAINTENANCE SECTION, Trinity County, Lufkin District |
| Let / began | 2025-08-20 / 2025-09-22 |
| Latest estimate | 2026-10-05 |
| Contract number | 8251107 |

## Why this score


Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.