# Texas Materials Group, INC.: TxDOT rehabilitation of existing road contract 46% complete, FM 55, Ellis County ($8,638,301, 7 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Fortson Contracting, INC. (1.85%); West Texas Rumble Strip LLC (0.31%); 4e Tree Worx LLC (0.66%); Mobile Enterprises, INC. (0.2%); Highway Traffic Control & Services, LLC (0.29%); Elite Striping, LLC (0.72%); Jr West Texas Concrete LLC (17.21%) |
| Progress | 46.28% complete, 45.86% of time used |
| Amount | $8,638,301 revised (original $8,523,201) |
| Paid to date | $3,944,674 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 55, SH 34 to NAVARRO COUNTY LINE, Ellis County, Dallas District |
| Let / began | 2025-10-08 / 2026-02-17 |
| Latest estimate | 2026-10-05 |
| Contract number | 10253008 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.