# Texas Materials Group, INC.: TxDOT rehabilitation of existing road contract 8% complete, IH 35, Bexar County ($2,844,607, 4 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Interstate Barricades & Markings, INC. (0%); Southwest Road & Safety Contractors, LTD. (0%); Linear Traffic Markings LLC (0%); Myers Concrete Construction, LP (0%) |
| Progress | 8.39% complete, 53.62% of time used |
| Amount | $2,844,607 revised (original $2,846,602) |
| Change orders | $-1,994 |
| Paid to date | $238,541 |
| Work | Rehabilitation Of Existing Road |
| Location | IH 35, SOMERSET ROAD to LP 13, Bexar County, San Antonio District |
| Let / began | 2025-10-09 / 2026-06-01 |
| Latest estimate | 2026-10-05 |
| Contract number | 10253212 |

## Why this score
- Contract over $1M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.