# Texas Materials Group, INC.: TxDOT maintenance contract 94% complete, US0059, Polk County ($1,749,469)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Progress | 94.47% complete, 74.17% of time used |
| Amount | $1,749,469 revised (original $583,920) |
| Change orders | $1,165,550 |
| Paid to date | $1,652,719 |
| Work | Maintenance |
| Location | US0059, POLK COUNTY MAINTENANCE YARD, Polk County, Lufkin District |
| Let / began | 2025-11-20 / 2026-01-07 |
| Latest estimate | 2026-10-05 |
| Contract number | 11251105 |

## Why this score
- Contract over $1M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.