# Texas Materials Group, INC.: TxDOT overlay contract 84% complete, IH 69, Harris County ($45,321,550, 9 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Scott Derr Painting Co, LLC (0.21%); American Concrete Company (1.67%); Mc2 Civil, LLC (8.44%); Cpave, INC. (0.21%); Southwest Road & Safety Contractors, LTD. (1.66%); Trp Construction Group, LLC (3.68%); Kingz Industrial LLC (2.85%); Dustrol, INC. (0.22%); Highway 1 LLC (3.71%) |
| Progress | 83.96% complete, 82.81% of time used |
| Amount | $45,321,550 revised (original $44,841,587) |
| Change orders | $179,961 |
| Paid to date | $37,798,098 |
| Work | Overlay |
| Location | IH 69, S OF BISSONNET to N OF SOUTH RICE AVE, Harris County, Houston District |
| Let / began | 2025-01-07 / 2025-04-13 |
| Latest estimate | 2026-09-30 |
| Contract number | 1253004 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.