# Texas Materials Group, INC.: TxDOT rehabilitation of existing road contract 83% complete, SS 73, Ellis County ($4,024,255, 9 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Jr West Texas Concrete LLC (14.5%); Dustrol, INC. (4.45%); Fortson Contracting, INC. (0.45%); J. H. Oden Contracting Company (3.11%); West Texas Rock Resources, LLC (0.5%); Traffic Highway Maintenance, LLC (2.35%); Stripe-A-Zone, LLC (0.32%); Texas Traffic And Barricade, LLC (0.63%); Site Partners, LLC (0.64%) |
| Progress | 82.99% complete, 103.73% of time used |
| Amount | $4,024,255 revised (original $3,784,310) |
| Change orders | $106,946 |
| Paid to date | $3,229,171 |
| Work | Rehabilitation Of Existing Road |
| Location | SS 73, IH 35E to FM 877, Ellis County, Dallas District |
| Let / began | 2025-01-08 / 2025-04-28 |
| Latest estimate | 2026-10-05 |
| Contract number | 1253217 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.