# Texas Materials Group, INC.: TxDOT bridge replacement contract 99% complete, SH 124, Jefferson County ($7,770,405, 10 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Aggregate Technologies, INC. (0.35%); Traffic Signs & Lines, LLC (0.57%); West Texas Rock Resources, LLC (0.11%); Weber-Balke Foundation Company, INC (3.89%); American Remediation Options, INC. (2.69%); Tom-Mac, INC. (3.41%); Primate Construction, LP (0.05%); Kingz Industrial LLC (1.01%); Phoenix Pollution Control & Environmental Services, INC. (0.22%); (Inactive)mesa Rod Busters, INC. (0.39%) |
| Progress | 98.9% complete, 110.44% of time used |
| Amount | $7,770,405 revised (original $6,296,239) |
| Change orders | $1,474,166 |
| Paid to date | $7,684,553 |
| Work | Bridge Replacement |
| Location | SH 124, AT TAYLORS BAYOU to STR 201240036802027, Jefferson County, Beaumont District |
| Let / began | 2023-02-02 / 2023-04-28 |
| Latest estimate | 2026-10-02 |
| Contract number | 2233214 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.