# Texas Materials Group, INC.: TxDOT rehabilitation of existing road contract 83% complete, Various, Travis County ($9,199,901, 5 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Texas Materials Group, INC. |
| Subcontractors | Trp Construction Group, LLC (8.38%); Roadway Traffic Control LLC (0.55%); Dallas Lite And Barricade, INC. (1.1%); Alpha Paving Industries LLC (1.1%); Texop Construction (0.82%) |
| Progress | 82.97% complete, 89.39% of time used |
| Amount | $9,199,901 revised (original $7,676,625) |
| Change orders | $1,440,272 |
| Paid to date | $7,564,297 |
| Work | Rehabilitation Of Existing Road |
| Location | Various, VARIOUS LOCATIONS DISTRICTWIDE to ., Travis County, Austin District |
| Let / began | 2024-02-01 / 2024-07-01 |
| Latest estimate | 2026-09-30 |
| Contract number | 2243022 |

## Why this score
- Contract over $1M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.